Calculate the Critical path network and draw on the PowerPoint images Use the provided CPM Network** to complete the following
1 Critical path
2. Node numbers
3 Durations
4 Earliest / Latest start and finish for each activity
5 Float for each activity
6 Major milestones***
7 Total time to complete this delivery order
***Note[3]: A milestone is a significant point in the project. Highlighted at the event (node), a milestone is often identified after the completion of a major event (review, submission of a significant deliverable, completion of a major test/demonstration, …). It is a point where the Project Manager assesses the current state of the project before progressing forward.
Background reference (for time durations of CPN)
1. Perform independent research on each of the five candidate IR sensors (2 weeks each for the Red-Eye series, one week each for the others).
2. Perform a trade study to down select to two IR sensor candidates (1.5 weeks).
3. Develop performance models for both IR sensor candidate sensors (6 weeks each). Note: These should be done separately but can be accomplished in parallel.
4. Develop a CONOPS to determine how IR / optical sensors are to be used on the X-65B (8 weeks).
5. Use the CONOPS and IR sensor performance models to develop / run independent performance simulations (4 weeks each). Note: These should be done separately but can be accomplished in parallel.
6. Use the outcome of your simulations as an input for a technical review to down select to a single IR sensor (preparations – 2 weeks).
7. Hold the IR sensor review and down select to a single IR sensor (1 day)
8. Perform research on the Eagle-Eye 2000® optical sensor (4 weeks).
9. Develop a performance model for the Eagle-Eye 2000® (2 weeks).
10. Update the performance model for the Tiger-Eye 1000® optical sensor (1 day).
11. Use the CONOPS and performance models to develop / run independent performance simulations (Tiger-Eye 1000® – 2 weeks, Eagle-Eye 2000® – 5 weeks)
12. Use the outcome of your simulations as an input for a technical review to down select to a single optical sensor (preparations – 2 weeks).
13. Hold the optical sensor review and down select to a single optical sensor (1 day). Please note that the IR sensor review and optical sensor review must be held separately but can occur in parallel. Page 2 Module 4 Assignment Building a Critical Path Network Management of Systems Projects Version 005_00b Revision
14. Design a common prototype hardware integration package to allow the selected IR / optical sensor to be mounted in the X65B. This mounting package must be designed in such a way to mount either the selected IR or optical sensor (dual use) (10 weeks). Note: This includes the development of a prototype to be used for hardware integration package testing (item15).
15. Test the hardware integration package and make required modifications (2 weeks).
16. Build three hardware integration packages (2 weeks total)
. 17. Design software to integrate the selected IR sensor with the X-65B mission computer (12 weeks).
18. Code IR sensor integration software (4 weeks).
19. Perform IR sensor software integration testing with the IR sensor and the X-65B simulator (3 weeks).
20. Design software to integrate the selected optical sensor with the X-65B mission computer (13 weeks).
21. Code optical sensor integration software (2 weeks).
22. Perform optical sensor software integration testing with the optical sensor and the X-65B simulator (3 weeks).
23. Install IR and optical sensors on the X-65B (2 days each – this can be done simultaneously, if required)
. 24. Perform final IR payload integration testing with the X-65B aircraft and make required changes (2 weeks).
25. Perform final optical payload integration testing with the X-65B aircraft and make required changes (2 weeks).
26. Develop test plan for X-65B live sensor testing (sensor independent – not dependent on selected sensors) (12 weeks).
27. Using the test plan, perform required hazard / safety analysis (3 weeks).
28. After completing the hazard / safety analysis, attain live sensor testing approval (6 weeks).
29. Perform X-65B live sensor tests (both sensors simultaneously) (2 weeks).
30. Develop live demonstration* plan, based on the outcome of the X-65B live sensor tests (1 week).
31. Make final changes to sensor payload configurations, based on live sensor tests (2 weeks).
32. Hold live demonstration* review (everything must be ready before this review occurs) (2 days).
33. Perform a practice series of dry run demos in preparation for the formal demonstration* (1 week).
34. *Perform live sensor demonstration (1 day).
35. Perform “hot wash” meeting after demonstration (1 day).
36. Write final close-out report, based on “hot wash” meeting (1 week).
Our Advantages
Plagiarism Free Papers
We ensure that all our papers are written from scratch. We deliver original plagiarism-free work. To guarantee this, we submit all work alongside a plagiarism report.
Free Revisions
All our papers are completed and submitted before the deadline. We ensure this to provide you with enough time to go through the work and point out any sections or topics that may need revision or polishing. We provide unlimited revision services for free.
Title-page
All papers have a title page providing your personal and institutional information. We do not charge you for this title page.
Bibliography
All papers have a bibliography or references page. This page is a requirement for academic and professional documents. We provide this page at no cost for all our papers.
Originality & Security
At Thehomeworklabs, we guarantee the confidentiality and security of your information. We value our clients and take confidentiality seriously. All personal information is treated with confidentiality and stored safely to ensure that no third parties gain access to it. We also provide original work and attach an originality/plagiarism report alongside all papers.
24/7 Customer Support
Our customer support team is available 24/7 to provide you with any necessary assistance when you need it. You can contact us at any time, day or night, via email or through the live chat button.
Try it now!
How it works?
Follow these simple steps to get your paper done
Place your order
Fill in the order form and provide all details of your assignment.
Proceed with the payment
Choose the payment system that suits you most.
Receive the final file
Once your paper is ready, we will email it to you.
Our Services
We provide our customers with the best experience in the academic and business writing field.
Pricing
We provide the best quality of service at affordable prices. We also allow our clients to make partial payments for their orders. You can also contact our customer support team in case you need to discuss a different payment plan.
Communication
Admission help & Client-Writer Contact
We realize that sometimes clarification is necessary to ensure that quality work is done. Therefore, we provide a button for clients and writers to communicate in case some clarification is needed.
Deadlines
Paper Submission
We ensure that we submit all papers ahead of their respective deadlines. This allows you to go through the documents and request any revision, corrections, or polishing before the paper is due.
Reviews
Customer Feedback
We encourage customer feedback, positive or negative. We can identify the various areas that we need to improve to provide even better services through your feedback. Please feel free to give us feedback.